This is the Sunzilla 3.0 assembly manual with Safety Instructions. This manual explains how to commission and decommission the SunZilla 3.0. and includes imporant safety information. PLEASE DO NOT ATTEMPT TO USE THE SUNZILLA 3.0 UNTIL YOU HAVE READ THIS MANUAL!
This is the Sunzilla 3.0 assembly manual with Safety Instructions. This manual explains how to commission and decommission the SunZilla 3.0. and includes imporant safety information. PLEASE DO NOT ATTEMPT TO USE THE SUNZILLA 3.0 UNTIL YOU HAVE READ THIS MANUAL!
Maximum AC-output of pure sinus inverter: 350W (700W peakload)
Effectiv battery storage: 600 Wh
Matériaux
Get the three boxes :
1. The left one (A) is the battery box
2. The mid- dle one (B) the solar box
3. The right one (C) the socket box
Open the solar module box, and get the solar cells, the cables, the aluminium profiles and the 8 screws outside.
Outils
Étape 1 - Connect the three boxes
Press the cable inside when both white points match and turn the blue top unit of the cable to lock.
Étape 2 - Close the solar module box
Close the solar module box, put the two long aluminium profiles in their holes. Open slightly the box and insert two screws to lock the profiles. Choose the same holes in the middle and be sure to do the same on both sides.
Étape 3 - Insert the aluminium profiles
Take the shorter aluminium profiles, insert them as shown on the pic and lock them.
Étape 4 - Pull down the elastic bands
Étape 5 -
Take the solar cells. Unfold them and shift the aluminium edges at all four sides
Étape 6 -
Take the upper part of the solar module and connect the whole solar module with the upper aluminium profile. Be sure that the solar module is on the left side of the aluminium profile. Connect also the lower part.
Étape 7 -
Connect the cables from the solar cells to the solar module box.
Étape 8 - Switch on battery box
Switch on battery box. Green light should turn on
Étape 9 - Switch on socket box
Switch on socket box. Green light should turn on
Étape 10 - Plug in consumer
Étape 11 - Dismanteling
{{{1}}}
At Dismanteling, you MUST follow the right order of these steps, otherwise you could be hurt.
Étape 12 - Switch off Socket Box if switched on
Switch off Socket Box if switched on
Étape 13 - Turn Solar Panels out of sun
Turn Solar Panels out of sun and cover at least one Solar-Panel (for exam- ple with Pullover)
Étape 14 - Disconnect Solar-Connectors
Étape 15 - Switch off Battery box
Étape 16 - Unplug / detach orange cables
Étape 17 - Switch on Socket box again
Switch on Socket box again until green light is off (to discharge local en-
ergy storage), then switch OFF again!
YOU’RE DONE!
Commentaires
×
Erreur de saisie dans le nom du tutoriel
Vous avez entré un nom de page invalide, avec un ou plusieurs caractères suivants :
< > @ ~ : * € £ ` + = / \ | [ ] { } ; ? #
Connexion
Pas encore enregistré ? Créez un compte pour profiter de toutes les fonctionnalités du service !